Licensed Legal Consultancy · Dubai Bay Square, Business Bay +971 50 555 12 47

UAE case law

Arbitration Clause and a Parallel Lawsuit in Another Court: a 2025 DIFC Ruling

Two shareholders in a joint venture fell out over who controlled a shared facility. One started arbitration under the agreement, and the other sued in a court in a neighbouring emirate. In 2025 the DIFC Court ordered that lawsuit to stop. Where a contract has an arbitration clause, disputes go to arbitration, not to an ordinary court.

ALROA Tasis · Updated

In short

In 2025 the DIFC Court restrained a joint-venture shareholder from pursuing a parallel lawsuit in another emirate because the agreement contained an arbitration clause seated in the DIFC. The shareholder could show no good or strong reason not to honour it. The court also awarded the other side its legal costs in full.

or assess your situation in 1 minute →
Arbitration Clause and a Parallel Lawsuit in Another Court: a 2025 DIFC Ruling

The background

Two shareholders owned a company 49% and 51% under a joint venture agreement. Board decisions had to be unanimous and shareholder decisions needed a 75% majority. Neither side could push anything through without the other, so the company was deadlocked, including over who could speak for it.

The minority shareholder ran the company's production facility under a separate operating contract. The majority shareholder came to regard that contract as unfavourable and accused the operator of irregularities. The minority shareholder went to the DIFC Court and obtained an urgent order. Until the arbitration was decided, nobody could change the management of the facility or the bank signatories, or push out the operator outside the agreed process.

The minority shareholder then served a dispute notice, waited for the pre-arbitration period to expire and filed for arbitration with an arbitration centre in Dubai. While the tribunal was being formed, the majority shareholder, claiming to act for the company, sued in a court of first instance in another emirate. It asked for a court expert committee, a handover of the facility, a ban on the operator signing documents, and its own temporary appointment as manager. That claim was dismissed, and the shareholder appealed.

The issue

The DIFC Court had to decide whether a party that agreed to arbitration seated in the DIFC could also sue in a local court of another emirate. It also had to decide which test applies: must the applicant prove that the lawsuit is “vexatious or oppressive”, or is the breach of the arbitration agreement enough?

The majority shareholder argued that it was simply exercising its rights as an owner. It wanted documents and an expert, not to remove the operator. It also pointed to the operating contract, which gave jurisdiction to the courts of the other emirate.

What the court decided and why

The court granted an anti-suit injunction: the defendants could not continue the parallel proceedings. It reached this in several steps.

  1. The main contract. An earlier ruling had already held that the joint venture agreement was the overarching agreement and that the clause on the other emirate's courts could not override arbitration. An application to appeal was pending, but the finding binds the parties until an appeal succeeds.
  2. The operating contract argument. Because the joint venture agreement was the main contract, the reliance on another contract with a different court clause fell away.
  3. The test. Where the seat is the DIFC, the court protects the parties' bargain. The applicant does not need to show that the other lawsuit is vexatious. The party in breach must show good or strong reasons not to honour the arbitration agreement, and there were none.
  4. Who the order is aimed at. The order is directed at the party who promised to arbitrate, not at the other court. The court holds that party to its agreement.
  5. The narrowed claims. The defendants cut their claim down to an expert and document requests. The court treated this as an admission that the original claims were improper, but the question of the right forum remained. Document requests and expert inspection belong in the arbitration, and if a request is truly urgent, an emergency arbitrator can be asked for relief.
  6. No prejudice. The tribunal can protect the defendants' interests, so enforcing the clause deprives them of nothing.
  7. Costs. The court awarded the claimant its costs in full, around AED 195,000, straight away rather than at the end of the arbitration, because the defendants had breached earlier court orders.

The court did not decide the parties' mutual allegations of bad faith, because they did not affect the outcome. It also removed the reference to prison from the warning on the order. The warning still mentions possible referral to the Attorney General of Dubai, a fine, or seizure of assets.

The rules the court applied

The court relied on the DIFC Arbitration Law (Law No. 1 of 2008). Under Article 24(3), the DIFC Court has the same power to grant interim measures in support of arbitration as it has in ordinary proceedings, wherever the arbitration is seated. Under Article 13(1), if a claim is brought on a matter covered by an arbitration agreement, the court must, if a party asks in time, dismiss or stay it unless the agreement is null and void, inoperative or incapable of being performed.

The court noted that the UAE Federal Arbitration Law has a similar rule in Article 8(1): a court dismisses the claim if the defendant objects before arguing the merits, unless the agreement is void or unenforceable. So both DIFC and federal courts must turn away claims brought in breach of an arbitration agreement. This is a paraphrase, so check the official text for the exact wording.

What this means for business

An arbitration clause works like an exclusive jurisdiction clause: once signed, you cannot choose to go to an ordinary court instead. Trying to get round it through another emirate's courts can be expensive.

  • Breaching a court order can lead to fines, asset seizure or referral to the prosecutor.
  • Costs may be awarded immediately and in full.
  • Where several agreements, such as a joint venture agreement and an operating contract, have different dispute clauses, parallel proceedings become likely, and it matters which document is the main one.
  • A 49/51 split with unanimity at board level and 75% at shareholder level can paralyse a company. Information and audit rights should be written into the agreement in advance and tied to arbitration.

How to avoid ending up here

  • Align the dispute clauses across all related contracts and state which document prevails.
  • Specify the seat, rules, number of arbitrators and language clearly.
  • Build in a deadlock-breaking mechanism: escalation, an independent director, a casting vote or a buy-out option.
  • Spell out shareholders' rights to documents and audit, and how they are exercised.
  • Take legal advice before filing in a local court when an arbitration clause exists.
  • If something is urgent, consider an emergency arbitrator or interim relief from the court of the seat.
  • Comply with court orders even while challenging them: until set aside, they stand.

How we can help

If you are setting up a joint venture, the lawyers at ALROA Tasis can help draft the shareholders' agreement and contracts so that dispute clauses do not conflict. As one of the consulting companies in the UAE offering legal support, we also handle shareholder disputes and act in DIAC and DIFC-LCIA arbitration. The outcome of any dispute depends on its facts, and we cannot guarantee a result.

FAQ

Generally not. If the other side objects, the court must dismiss or stay the case, and where the seat is the DIFC the court may also restrain you from continuing. The exception is where the clause is void or cannot be performed.

It is a court order telling a party not to start or continue a lawsuit elsewhere. It is aimed at the party who promised to arbitrate, not at the other court.

Not in this case. Where the seat is the DIFC, the court asks whether the party in breach has good or strong reasons not to honour the clause. Whether the lawsuit is vexatious is not the test.

You can ask for an emergency arbitrator and, where needed, for interim relief from the court of the seat. A claim on the merits in an ordinary court is not the way.

The court can refer the matter to the Attorney General, impose a fine or order seizure of assets. In this case it also awarded the other side's costs in full straight away.

This material is for information only and is not legal advice. UAE authorities' rules and requirements change — check the current version before acting.

Online check

Assess your situation

3 questions — and you'll see the plan, timing and an indicative price. A lawyer will review your answers and contact you the way you prefer.

  • Indicative timing and price right away, before any call
  • The lawyer's initial assessment is free
  • We contact you only via the messenger you choose
  • Confidential: no data shared with third parties

Tell us about your case

Describe the matter in a few words. A lawyer will get back to you and explain how we can help.

  • AddressBay Square, Business Bay, Dubai, UAE
  • HoursMon–Fri, 9:00–18:00 (GMT+4)
  • Phone+971 50 555 12 47
  • WhatsApp+971 50 555 12 47
  • Telegram@as7winds
  • Emailinfo@dubailegal.ru

Consultation request

Skip sensitive personal details. We will go through them on the call.
Request sent. A lawyer will contact you within 30 minutes during office hours.